Irganayskaya Hydro Power Plant
Hydraulic engineering works
Underground structures of various application, Chief Project Engineer - M. Faskheev.
Projection of the underground HPP facilities building organization and technology, the waterworks underground structures construction development.
Development and implementation of:
- Technology of building the derivation tunnel (5.2 km) with the use of mechanized tunneling complex (diameter of 8.5 meters);
- Design and installation technology of the steel - polymer anchors as elements of a temporary support;
- Composition and application technology of a "wet" spray concrete as a part of a temporary support;
- Technology of concrete lining the tunnel with the use of mobile mechanized formwork (length 20 m.)
1985 - 1998.